Dept. of Trans. PROGRESS Serial No. Contract No. 22-077-08-57 07-4V3604 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 24% Location: Federal Project: 07-LA-138-59.1/60.2 NONE Progress payment No. 001 Payment period ending: 03-20-22 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 77,490.00 77,490.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 77,490.00 77,490.00 5. Mobilization 6. Total Work Completed 77,490.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 77,490.00 77,490.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,490.00