Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-15-02 07-4V4204 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 79% Location: Federal Project: 07-LA-710-6.2/7.2 NONE Progress payment No. 011 Payment period ending: 09-20-24 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 349,399.00 15,090.00 2. a. Extra Work 243,022.94 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 592,421.94 15,090.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 622,421.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 622,421.94 15,090.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,090.00