Dept. of Trans. PROGRESS Serial No. Contract No. 25-056-21-13 07-4V4204 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 79% Location: Federal Project: 07-LA-710-6.2/7.2 NONE Progress payment No. 016 Payment period ending: 02-20-25 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 463,920.80 4,730.40 2. a. Extra Work 259,220.43 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 723,141.23 4,730.40 5. Mobilization 30,000.00 0.00 6. Total Work Completed 753,141.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 753,141.23 4,730.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,730.40