Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-14-23 07-4V4204 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 79% Location: Federal Project: 07-LA-710-6.2/7.2 NONE Progress payment No. 020 Payment period ending: 06-20-25 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 482,842.40 4,730.40 2. a. Extra Work 282,935.11 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 765,777.51 4,730.40 5. Mobilization 30,000.00 0.00 6. Total Work Completed 795,777.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 795,777.51 4,730.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,730.40