Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-00-35 07-4V4304 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 42% Location: Federal Project: 07-LA-405-30.1/33.0 NONE Progress payment No. 003 Payment period ending: 11-20-23 KORMEX CONSTRUCTION INC 2324 S VINEYARD AVE #K ONTARIO CA 91761 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 530,190.00 181,415.00 2. a. Extra Work 22,165.50 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 552,355.50 181,415.00 5. Mobilization 35,000.00 0.00 6. Total Work Completed 587,355.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 587,355.50 181,415.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,415.00