Dept. of Trans. PROGRESS Serial No. Contract No. 25-198-13-16 07-4V4904 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 57% Location: Federal Project: 07-LA-105-R17.5/R17.8 NONE Progress payment No. 011 Payment period ending: 07-20-25 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 559,122.00 2,770.00 2. a. Extra Work 20,494.16 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 579,616.16 2,770.00 5. Mobilization 33,000.00 0.00 6. Total Work Completed 612,616.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 612,616.16 2,770.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,770.00