Dept. of Trans. PROGRESS Serial No. Contract No. 25-294-19-14 07-4V5004 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 07-LA-210-R24.7/R25.3 NONE Progress payment No. 003 Payment period ending: 10-20-25 CALMEX ENGINEERING INC 2750 S LILAC AVE BLOOMINGTON CA 92316 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 704,692.49 165,649.29 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 704,692.49 165,649.29 5. Mobilization 37,500.00 0.00 6. Total Work Completed 742,192.49 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 742,192.49 165,649.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 165,649.29