Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-15-39 07-4V5204 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 4% Location: Federal Project: 07-LA-138-59.7 NONE Progress payment No. 002 Payment period ending: 06-20-25 POLO ENGINEERING INC 30758 SLOAN CANYON RD CASTAIC CA 91384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,500.00 7,500.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 102,058.04 24,367.79 4. Earned Subject to Retention 109,558.04 31,867.79 5. Mobilization 71,250.00 23,750.00 6. Total Work Completed 78,750.00 7. Deductions -47,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 133,308.04 55,617.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,617.79