Dept. of Trans. PROGRESS Serial No. Contract No. 25-294-19-17 07-4V5204 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 34% Location: Federal Project: 07-LA-138-59.7 NONE Progress payment No. 006 Payment period ending: 10-20-25 POLO ENGINEERING INC 30758 SLOAN CANYON RD CASTAIC CA 91384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 757,092.34 310,857.90 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 56,400.89 -77,690.26 4. Earned Subject to Retention 813,493.23 233,167.64 5. Mobilization 95,000.00 0.00 6. Total Work Completed 852,092.34 7. Deductions -47,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 860,993.23 233,167.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 233,167.64