Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-17-21 07-4V5404 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 42% Location: Federal Project: 07-LA-5-R56.4/R56.7 SIMG-052(777) Progress payment No. 001 Payment period ending: 11-20-25 GENUINE ENGINEERING INC 11762 DE PALMA RD #1C-225 CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 613,368.75 613,368.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 613,368.75 613,368.75 5. Mobilization 88,000.00 88,000.00 6. Total Work Completed 701,368.75 7. Deductions -1,157.35 -1,157.35 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 700,211.40 700,211.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 700,211.40