Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-13-45 07-4W0904 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 62% Location: Federal Project: 07-LA-60-R0.6/R0.6 NONE 07-LA-91 07-LA-110 Progress payment No. 002 Payment period ending: 01-20-20 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 378,998.25 162,224.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 378,998.25 162,224.00 5. Mobilization 86,450.00 0.00 6. Total Work Completed 465,448.25 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 455,448.25 152,224.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 152,224.00