Dept. of Trans. PROGRESS Serial No. Contract No. 20-296-15-14 07-4W0904 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 79% Location: Federal Project: 07-LA-60-R0.6/R0.6 NONE 07-LA-91 07-LA-110 Progress payment No. 009 Payment period ending: 10-20-20 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 793,054.95 12,710.50 2. a. Extra Work 25,081.11 1,263.76 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 818,136.06 13,974.26 5. Mobilization 91,000.00 0.00 6. Total Work Completed 909,136.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 909,136.06 13,974.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,974.26