Dept. of Trans. PROGRESS Serial No. Contract No. 18-204-14-55 07-4W2104 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 45% Location: Federal Project: 07-LA-10-17.0/48.3 NONE Progress payment No. 001 Payment period ending: 07-20-18 PAVE-TECH INC 2231 LA MIRADA DRIVE VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 532,853.60 532,853.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 532,853.60 532,853.60 5. Mobilization 444,450.00 444,450.00 6. Total Work Completed 977,303.60 7. Deductions -63,930.00 -63,930.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 913,373.60 913,373.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 913,373.60