Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-16-59 07-4W2804 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 76% Location: Federal Project: 07-VEN-33-6.3/11.2 NONE Progress payment No. 004 Payment period ending: 05-20-19 VSS INTERNATIONAL INC 3785 CHANNEL DRIVE WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 557,574.06 18,427.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 557,574.06 18,427.50 5. Mobilization 171,736.25 0.00 6. Total Work Completed 729,310.31 7. Deductions -44,804.85 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 49,448.75 c. Reduction after 95% Comp. 9. Total pay to Contractor 684,505.46 67,876.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,876.25