Dept. of Trans. PROGRESS Serial No. Contract No. 19-169-10-55 07-4W2804 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 87% Location: Federal Project: 07-VEN-33-6.3/11.2 NONE Progress payment No. 005 Payment period ending: 06-20-19 VSS INTERNATIONAL INC 3785 CHANNEL DRIVE WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 825,229.23 267,655.17 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 825,229.23 267,655.17 5. Mobilization 180,775.00 9,038.75 6. Total Work Completed 1,006,004.23 7. Deductions -47,163.00 -2,358.15 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 958,841.23 274,335.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 274,335.77