Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-259-15-03 07-4W4604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-405-8.2/8.2 NONE Progress payment No. 010 Payment period ending: 06-22-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,487,131.06 -13,171.90 2. a. Extra Work 3,745.97 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,490,877.03 -13,171.90 5. Mobilization 230,000.00 0.00 6. Total Work Completed 3,720,877.03 7. Deductions -44,200.00 62,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,676,677.03 48,828.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,828.10