Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-10-05 07-4W5504 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 46% Location: Federal Project: 07-LA-210-R24.6/R51.9 NONE Progress payment No. 003 Payment period ending: 11-20-20 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 410,756.10 186,046.27 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 410,756.10 186,046.27 5. Mobilization 80,750.00 0.00 6. Total Work Completed 491,506.10 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 488,506.10 183,046.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,046.27