Dept. of Trans. PROGRESS Serial No. Contract No. 22-326-15-34 07-4W7804 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 60% Location: Federal Project: 07-LA-110-6.8/19.5 NONE Progress payment No. 004 Payment period ending: 11-20-22 AUTOBAHN CONSTRUCTION, INC PO BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 764,290.86 210,246.16 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 254,300.00 -23,613.00 4. Earned Subject to Retention 1,018,590.86 186,633.16 5. Mobilization 142,500.00 0.00 6. Total Work Completed 906,790.86 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,161,090.86 186,633.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,633.16