Dept. of Trans. PROGRESS Serial No. Contract No. 20-297-14-03 07-4W8204 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 14% Location: Federal Project: 07-VEN-101-17.7/17.7 NONE Progress payment No. 003 Payment period ending: 10-20-20 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 340,254.80 327,054.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 340,254.80 327,054.80 5. Mobilization 61,573.30 61,573.30 6. Total Work Completed 401,828.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 401,828.10 388,628.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 388,628.10