Dept. of Trans. PROGRESS Serial No. Contract No. 21-202-16-57 07-4W9104 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 17% Location: Federal Project: 07-VEN-101-9.1/9.1 NONE Progress payment No. 001 Payment period ending: 07-20-21 JABRE CONTRACTING INC 1813 MANZANITA LN MANHATTAN BEACH CA 90266 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 174,138.00 174,138.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 174,138.00 174,138.00 5. Mobilization 68,400.00 68,400.00 6. Total Work Completed 242,538.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 242,538.00 242,538.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 242,538.00