Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-011-08-34 07-4W9104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-VEN-101-9.1/9.1 NONE Progress payment No. 010 Payment period ending: 12-11-23 JABRE CONTRACTING INC 1813 MANZANITA LN MANHATTAN BEACH CA 90266 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 678,853.00 35.00 2. a. Extra Work 19,793.64 0.00 b. Adustment Comp. 318,027.16 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,016,673.80 35.00 5. Mobilization 72,000.00 0.00 6. Total Work Completed 1,088,673.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,088,673.80 35.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35.00