Dept. of Trans. PROGRESS Serial No. Contract No. 15-056-08-34 07-4X1304 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 100% Location: Federal Project: 07-LA-710-22.6/23.0 NONE Progress payment No. 009 Payment period ending: 02-20-15 SHIMMICK/MYERS AND SONS JV 16481 SCIENTIFIC WAY IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 633,840.72 35,509.04 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 633,840.72 35,509.04 5. Mobilization 6. Total Work Completed 633,840.72 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 623,840.72 25,509.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,509.04