Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-15-01 07-4X3304 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 33% Location: Federal Project: 07-LA-105-8.0/10.2 NONE 07-LA-170-19.7/19.7 Progress payment No. 002 Payment period ending: 04-20-15 WEST COAST STRUCTURES INC DBA WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE, CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 387,581.88 385,423.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 387,581.88 385,423.16 5. Mobilization 6. Total Work Completed 387,581.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 387,581.88 385,423.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 385,423.16