Dept. of Trans. PROGRESS Serial No. Contract No. 15-309-14-18 07-4X5404 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 10% Location: Federal Project: 07-LA-101-9.2/38.2 NONE Progress payment No. 001 Payment period ending: 11-05-15 LANDSCAPE SUPPORT SERVICES 15260 VENTURA BLVD #1150 SHERMAN OAKS, CA 91403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 201,276.45 201,276.45 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 201,276.45 201,276.45 5. Mobilization 6. Total Work Completed 201,276.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 201,276.45 201,276.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 201,276.45