Dept. of Trans. PROGRESS Serial No. Contract No. 16-174-14-13 07-4X5504 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 42% Location: Federal Project: 07-LA-134-5.6/9.0 NONE 07-LA-110-24.7/24.7 Progress payment No. 006 Payment period ending: 06-20-16 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 301,354.00 71,285.31 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 301,354.00 71,285.31 5. Mobilization 6. Total Work Completed 301,354.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 301,354.00 71,285.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,285.31