Dept. of Trans. PROGRESS Serial No. Contract No. 16-083-13-15 07-4X6704 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 96% Location: Federal Project: 07-LA-2-64.0/82.3 NONE Progress payment No. 004 Payment period ending: 03-20-16 IBARRA GENERAL ENGINEERING INC 12531 SAN MINA CT CHINO CA 91710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 648,676.59 41,071.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 648,676.59 41,071.65 5. Mobilization 6. Total Work Completed 648,676.59 7. Deductions -2,182.00 -2,182.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 646,494.59 38,889.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,889.65