Dept. of Trans. PROGRESS Serial No. Contract No. 16-083-13-19 07-4X8004 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 52% Location: Federal Project: 07-VEN-101-32.2/34.8 NONE 07-VEN-1-21.5/21.5 Progress payment No. 001 Payment period ending: 03-20-16 SUMMER CONSTRUCTION INC 15245 TELEGRAPH RD SANTA PAULA CA 93060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 253,891.47 253,891.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 253,891.47 253,891.47 5. Mobilization 6. Total Work Completed 253,891.47 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 253,891.47 253,891.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 253,891.47