Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-259-10-27 07-4Y1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-126-30.3/34.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-29-11 VALLEY SLURRY SEAL COMPANY PO BOX 981330 WEST SACRAMENTO CA 95791 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 554,275.08 0.00 2.a. Extra Work b. Adjustment Comp. 18,083.09 18,083.09 3. Materials on Hand 4. Earned Subject to Retention 572,358.17 18,083.09 5. Mobilization 10,000.00 0.00 6. Total Work Completed 582,358.17 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 582,358.17 18,083.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,083.09