Dept. of Trans. PROGRESS Serial No. Contract No. 11-326-16-50 07-4Y1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 90% 07-LA-138-69.3/75.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-11 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE, CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 713,222.75 950.00 2.a. Extra Work 18,471.96 0.00 b. Adjustment Comp. 70,484.61 0.00 3. Materials on Hand 4. Earned Subject to Retention 802,179.32 950.00 5. Mobilization 35,000.00 0.00 6. Total Work Completed 837,179.32 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 837,179.32 950.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 950.00