Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-15-01 07-4Y2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 59% 07-LA-105-R4.7/R15.4 Federal Project: NONE Progress payment No. 05 Payment period ending: 08-20-11 WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 674,852.95 437,759.17 2.a. Extra Work 18,796.83 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 693,649.78 437,759.17 5. Mobilization 51,197.97 2,559.90 6. Total Work Completed 744,847.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 744,847.75 440,319.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 440,319.07