Dept. of Trans. PROGRESS Serial No. Contract No. 11-298-13-52 07-4Y2804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 97% 07-LA-101-11.8/35.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-11 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 339,580.55 283,569.66 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 339,580.55 283,569.66 5. Mobilization 53,390.00 25,290.00 6. Total Work Completed 392,970.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 392,970.55 308,859.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 308,859.66