Dept. of Trans. FINAL Serial No. Contract No. 11-357-11-42 07-4Y3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-110-28.1/30.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-21-11 CALIFORNIA BUILDERS GROUP INC 6133 BRISTOL PARKWAY, STE 270 CULVER CITY CA 90230 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 227,945.00 0.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 227,945.00 0.00 5. Mobilization 24,000.00 0.00 6. Total Work Completed 251,945.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 251,945.00 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00