Dept. of Trans. PROGRESS Serial No. Contract No. 10-265-16-25 07-4Y5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 7% 07-LA-47-0.9/2.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-10 SAFWAY SERVICES L P 601 WEST 140TH STREET GARDENA CA 90248 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 116,401.66 76,326.16 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 116,401.66 76,326.16 5. Mobilization 9,000.00 9,000.00 6. Total Work Completed 125,401.66 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 125,401.66 85,326.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,326.16