Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-13-09 07-4Y7004 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 30% Location: Federal Project: 07-LA-405-8.8/8.8 NHPI-405 2-975(E) Progress payment No. 002 Payment period ending: 06-20-16 MURPHY INDUSTRIAL COATINGS INC 2704 GUNDRY AVE SIGNAL HILL CA 90755 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,200.00 4,000.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 22,200.00 4,000.00 5. Mobilization 6. Total Work Completed 22,200.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,200.00 4,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,000.00