Dept. of Trans. FINAL Serial No. Contract No. 14-078-15-22 07-4Y7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-101-31.2/39.3 Federal Project: NONE Progress payment No. 09 Payment period ending: 05-21-13 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 418,116.59 0.00 2.a. Extra Work 137,028.91 0.00 b. Adjustment Comp. 1,072.03 1,072.03 3. Materials on Hand 4. Earned Subject to Retention 556,217.53 1,072.03 5. Mobilization 20,500.00 0.00 6. Total Work Completed 576,717.53 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 576,717.53 1,072.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,072.03