Dept. of Trans. PROGRESS Serial No. Contract No. 12-296-13-23 07-4Y8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 80% 07-LA-57-0.9/11.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-12 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 316,538.94 316,538.94 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 316,538.94 316,538.94 5. Mobilization 69,730.00 69,730.00 6. Total Work Completed 386,268.94 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -31,653.89 -31,653.89 c. Reduction after 95% Comp. 9. Total pay to Contractor 354,615.05 354,615.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 354,615.05