Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-008-15-14 07-4Y8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-57-0.9/11.6 Federal Project: NONE Progress payment No. 08 Payment period ending: 12-11-13 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 892,186.86 30,172.60 2.a. Extra Work 18,939.92 6,732.00 b. Adjustment Comp. 34,060.38 34,060.38 3. Materials on Hand 4. Earned Subject to Retention 945,187.16 70,964.98 5. Mobilization 73,400.00 0.00 6. Total Work Completed 1,018,587.16 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,018,587.16 70,964.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,964.98