Dept. of Trans. PROGRESS Serial No. Contract No. 16-265-13-14 07-4Y8504 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 15% Location: Federal Project: 07-LA-103-0.9/1.2 NHP-P103(4) Progress payment No. 003 Payment period ending: 09-20-16 CL COATINGS INC 8450 W 191ST ST UNIT 19 MOKENA IL 60448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,394.38 4,403.58 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 17,394.38 4,403.58 5. Mobilization 6. Total Work Completed 17,394.38 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,394.38 4,403.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,403.58