Dept. of Trans. PROGRESS Serial No. Contract No. 12-331-10-03 07-4Y9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 61% 07-LA-605-R0.8/25.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-20-12 VELARDE CONCRETE CONSTRUCTION INC 523 S BRAND BLVD SUITE 201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 723,280.60 59,545.63 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 723,280.60 59,545.63 5. Mobilization 82,500.00 0.00 6. Total Work Completed 805,780.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 805,780.60 59,545.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,545.63