Dept. of Trans. PROGRESS Serial No. Contract No. 12-202-14-31 07-4Y9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 24% 07-LA-2-15.3/23.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-12 WESTERN STRUCTURES 6005 TYLER ST RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 425,145.02 345,806.54 2.a. Extra Work 449.94 449.94 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 425,594.96 346,256.48 5. Mobilization 58,209.00 14,552.25 6. Total Work Completed 483,803.96 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 483,803.96 360,808.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 360,808.73