Dept. of Trans. PROGRESS Serial No. Contract No. 01-235-07-55 08-003114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 26% 08-RIV-15-19.9/21.5 Federal Project: NONE Progress payment No. 12 Payment period ending: 08-20-01 REYCO EROSION CONTROL 206 NORTH SMITH AVENUE CORONA CA 91720 Escrow No. 01572 Total Estimate This Estimate 1. Contract Itms Without Mobil. 575,697.00 900.00 2.a. Extra Work 11,525.59 0.00 b. Adjustment Comp. 10,100.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 597,322.59 900.00 5. Mobilization 10,000.00 0.00 6. Total Work Completed 607,322.59 7. Deductions -500.00 -500.00 8. a.Contract Retentions -29,866.13 -45.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 576,956.46 355.00 10. Reduction Amt to Escrow 11. Payment to Escrow 29,820.00 12. Net Pymt. this Estimate 355.00