Dept. of Trans. PROGRESS Serial No. Contract No. 00-207-06-49 08-006314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 5% 08-SBD-215-2.1/3.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-00 REYCO EROSION CONTROL 7030 HAWARDEN DR RIVERSIDE CA 92506 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 99,347.50 96,197.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 99,347.50 96,197.50 5. Mobilization 2,625.00 2,625.00 6. Total Work Completed 101,972.50 7. Deductions 8. a.Contract Retentions -9,934.75 -9,619.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 92,037.75 89,202.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,202.75