Dept. of Trans. PROGRESS Serial No. Contract No. 01-057-08-06 08-006314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 20% 08-SBD-215-2.1/3.2 Federal Project: NONE Progress payment No. 10 Payment period ending: 02-20-01 REYCO EROSION CONTROL 7030 HAWARDEN DR RIVERSIDE CA 92506 Escrow No. 01566 Total Estimate This Estimate 1. Contract Itms Without Mobil. 548,168.50 23,505.00 2.a. Extra Work 797.80 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 548,966.30 23,505.00 5. Mobilization 3,500.00 0.00 6. Total Work Completed 552,466.30 7. Deductions 8. a.Contract Retentions -27,448.32 -1,175.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 525,017.98 22,329.75 10. Reduction Amt to Escrow 11. Payment to Escrow 27,440.00 12. Net Pymt. this Estimate 22,329.75