Dept. of Trans. PROGRESS Serial No. Contract No. 00-207-06-49 08-007114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 99% 08-SBD-215-4.0/7.2 Federal Project: ACIM-215-1(204) ACIM-215-1(204) Progress payment No. 20 Payment period ending: 07-20-00 A F R CONSTRUCTION INC 11 N FIFTH AVE ARCADIA CA 91006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,581,151.92 182,766.04 2.a. Extra Work 105,823.42 7,127.26 b. Adjustment Comp. -543.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,686,432.29 189,893.30 5. Mobilization 511,000.00 0.00 6. Total Work Completed 5,197,432.29 7. Deductions -23,454.90 0.00 8. a.Contract Retentions -234,321.61 -9,494.66 b. Unsatisfactory Prog. -51,653.19 -9,494.67 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,888,002.59 170,903.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 170,903.97