Dept. of Trans. PROGRESS Serial No. Contract No. 00-236-08-54 08-007114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 99% 08-SBD-215-4.0/7.2 Federal Project: ACIM-215-1(204) ACIM-215-1(204) Progress payment No. 21 Payment period ending: 08-20-00 A F R CONSTRUCTION INC 11 N FIFTH AVE ARCADIA CA 91006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,650,049.60 68,897.68 2.a. Extra Work 107,951.22 2,127.80 b. Adjustment Comp. -1,263.05 -720.00 3. Materials on Hand 4. Earned Subject to Retention 4,756,737.77 70,305.48 5. Mobilization 511,000.00 0.00 6. Total Work Completed 5,267,737.77 7. Deductions -23,454.90 0.00 8. a.Contract Retentions -237,836.89 -3,515.28 b. Unsatisfactory Prog. -55,168.46 -3,515.27 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,951,277.52 63,274.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,274.93