Dept. of Trans. PROGRESS Serial No. Contract No. 00-270-10-12 08-007114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 08-SBD-215-4.0/7.2 Federal Project: ACIM-215-1(204) ACIM-215-1(204) Progress payment No. 22 Payment period ending: 09-20-00 A F R CONSTRUCTION INC 11 N FIFTH AVE ARCADIA CA 91006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,721,467.10 71,417.50 2.a. Extra Work 107,951.22 0.00 b. Adjustment Comp. -1,263.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,828,155.27 71,417.50 5. Mobilization 511,000.00 0.00 6. Total Work Completed 5,339,155.27 7. Deductions -23,454.90 0.00 8. a.Contract Retentions -241,407.76 -3,570.87 b. Unsatisfactory Prog. -58,739.34 -3,570.88 c. Reduction after 95% Comp. 9. Total pay to Contractor 5,015,553.27 64,275.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,275.75