Dept. of Trans. PROGRESS Serial No. Contract No. 00-327-14-45 08-007114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 08-SBD-215-4.0/7.2 Federal Project: ACIM-215-1(204) ACIM-215-1(204) Progress payment No. 24 Payment period ending: 11-20-00 A F R CONSTRUCTION INC 11 N FIFTH AVE ARCADIA CA 91006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,766,464.10 16,597.00 2.a. Extra Work 107,951.22 0.00 b. Adjustment Comp. -1,263.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,873,152.27 16,597.00 5. Mobilization 511,000.00 0.00 6. Total Work Completed 5,384,152.27 7. Deductions -23,454.90 0.00 8. a.Contract Retentions -243,657.61 -829.85 b. Unsatisfactory Prog. -60,989.19 -829.85 c. Reduction after 95% Comp. 9. Total pay to Contractor 5,056,050.57 14,937.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,937.30