Dept. of Trans. PROGRESS Serial No. Contract No. 09-085-13-31 08-007174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 45% 08-SBD-215-4.8/6.5 Federal Project: PNRS-6208(13) CML-6208(13) Progress payment No. 16 Payment period ending: 03-20-09 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,370,415.60 2,927,306.80 2.a. Extra Work 647,535.60 91,323.59 b. Adjustment Comp. 31,000.40 2,332.40 3. Materials on Hand 1,296,763.18 -186,655.82 4. Earned Subject to Retention 37,345,714.78 2,834,306.97 5. Mobilization 7,599,936.35 0.00 6. Total Work Completed 43,648,887.95 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,940,651.13 2,834,306.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,834,306.97