Dept. of Trans. PROGRESS Serial No. Contract No. 09-147-13-48 08-007174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 52% 08-SBD-215-4.8/6.5 Federal Project: PNRS-6208(13) CML-6208(13) Progress payment No. 18 Payment period ending: 05-20-09 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,990,017.77 3,686,745.18 2.a. Extra Work 765,841.42 103,632.22 b. Adjustment Comp. 57,860.91 25,090.11 3. Materials on Hand 1,555,047.24 312,652.46 4. Earned Subject to Retention 45,368,767.34 4,128,119.97 5. Mobilization 7,999,933.00 0.00 6. Total Work Completed 51,813,653.10 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 53,363,700.34 4,128,119.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,128,119.97