Dept. of Trans. PROGRESS Serial No. Contract No. 09-239-12-59 08-007174 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 63% 08-SBD-215-4.8/6.5 Federal Project: PNRS-6208(13) CML-6208(13) Progress payment No. 22 Payment period ending: 08-20-09 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,791,497.32 2,925,668.71 2.a. Extra Work 1,083,241.81 119,387.72 b. Adjustment Comp. 271,943.29 -52,529.29 3. Materials on Hand 959,348.55 -146,832.94 4. Earned Subject to Retention 55,106,030.97 2,845,694.20 5. Mobilization 7,999,933.00 0.00 6. Total Work Completed 62,146,615.42 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 63,100,963.97 2,845,694.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,845,694.20